Because billboards are typically near public transit, they are routinely impacted by public projects such as street widenings, highway and freeway expansions, and grade separation projects. When impacted, billboard companies may make claims for (i) the value of the billboard itself (fixtures and equipment), (ii) loss of business goodwill, and (iii) relocation expenses. Usually the first two items can be addressed through a successful billboard relocation. But when happens when a moratorium is in place prohibiting new billboards? Does a moratorium on new billboards prohibit a relocation, thereby forcing the public agency to pay the billboard companies large goodwill claims? The answer is that despite a billboard moratorium, a relocation may still take place, thereby limiting the agency's exposure.
The Outdoor Advertising Act provides:
It is a policy of this state to encourage local entities and display owners to enter into relocation agreements which allow local entities to continue development in a planned manner without expenditure of public funds while allowing the continued maintenance of private investment and a medium of public communication. [All] local entities are specially empowered to enter into relocation agreements on whatever terms are agreeable to the display owner and the . . . local entity, and to adopt ordinance or resolutions providing for relocation of displays.
(Bus & Prof. Code, § 5412.) A recent unpublished case, City of Corona v. AMG Outdoor Advertising (2016 Cal.App. Unpub. Lexis 147), confirmed that when "the owner of a preban or grandfathered billboard either wants to move it or has to move it because it will be condemned by eminent domain, [the Outdoor Advertising Act and the local entity's municipal code] authorize the [local entity] to negotiate the terms of the relocation."
For public agencies constructing public projects that involve the displacement of billboards, don't just assume a relocation is not possible due to a billboard moratorium. Check the local municipal code - it is likely that many have exceptions for relocation agreements. And start working on a relocation agreement early and explore alternatives that can allow the billboard to obtain a new, viable relocation site, thereby minimizing exposure to large claims.
- Partner
Brad Kuhn, chair of Nossaman's Eminent Domain & Inverse Condemnation Group, is a nationally-recognized leader in the areas of eminent domain/inverse condemnation, land use/zoning and other property and business disputes. Brad ...
Eminent Domain Report is a one-stop resource for everything new and noteworthy in eminent domain. We cover all aspects of eminent domain, including condemnation, inverse condemnation and regulatory takings. We also keep track of current cases, project announcements, budget issues, legislative reform efforts and report on all major eminent domain conferences and seminars in the United States.
Stay Connected
RSS FeedCategories
- Administration
- Appraisal
- California
- CLIMATE CHANGE
- CONGRESS
- Construction
- Court Decisions
- EPA
- Events
- Goodwill
- GOVERNMENT ADMINISTRATION
- Inverse Condemnation & Regulatory Takings
- Lawsuit
- New Legislation
- Possession
- Projects
- Public Agency Law
- Publications
- Redevelopment
- Regulatory Reform and Proposed Rules
- Right to Take
- Right-of-Way
- Seminars
- Speaking Engagements and Presentations
- Valuation
- Videos
- Water